How to hire electricians when data centers pull every hand

The data center electrician shortage in numbers: spending up 73% in a year. What a shop without data center work can still offer a journeyman.

Updated November 9, 202612 min read8 sources

Photo: Chris Rycroft, Wikimedia Commons (CC BY 2.0)

You won't outbid a data center job on rate alone, so sell what it can't give a journeyman: home every night, a steady backlog, a next job, a rate that holds and a foreman worth working for. The pull is real. Private data center construction spending hit $84.95 billion a year in August 2026, up 73% from $49.05 billion a year earlier (Census Bureau, seasonally adjusted annual rate).

01How big is the data center pull?

It's the fastest-growing piece of private construction, and it's growing while chip plant work shrinks.

These are Census Bureau figures for private construction spending, seasonally adjusted annual rate, in billions. August 2026 is preliminary.

August ofData centersElectric powerComputer, electronic and electrical plants (chip fabs)
2021$10.5$90.3$10.9
2022$13.1$93.1$45.1
2023$20.5$113.0$100.9
2024$36.7$124.9$123.3
2025$49.1$127.4$95.4
2026$85.0$141.2$52.3

Three things jump out (our math from the table):

  • Data center spending is about 8 times what it was in August 2021.
  • Computer, electronic and electrical plant spending (where the chip fabs sit) fell by more than half from August 2024 ($123.3 billion) to August 2026 ($52.3 billion).
  • Electric power construction is up 56% over the same five years.

ABC, reading the same Census release on October 1, 2026, said data center spending has grown at a 149% annualized pace since March. Its chief economist, Anirban Basu, put it this way: "Frankly, it's becoming difficult to contextualize the size and speed of this boom."

For the full picture of why hands are hard to find this year, start with the 2026 electrician shortage numbers.

02Who is getting the data center work?

Mostly the big contractors, and that's who is pulling hands away from everyone else.

ABC's Construction Backlog Indicator for September 2026 (released October 13) found:

  • 15% of ABC members are under contract for data center work.
  • 39% of contractors with more than $100 million in revenue have data center work, against about 1 in 10 under $100 million.
  • Firms with data center work average 11.3 months of backlog, "a full three months more" than firms without.

So a large shop with almost a year of work booked is hiring from the same pool you are. If you're under $100 million, odds are you're not on those jobs, but your hands still get the calls.

03Small commercial work is going begging

While the big shops chase data centers, the small commercial jobs they used to bid are sitting with nobody to do them. One commercial contractor who does tenant finish-out, offices, restaurants and bars told us his GCs "can't find anyone to do that. Everyone's chasing the data centers and schools."

He gets about 20 emails a day from GCs asking for a price. One GC told him a job bid at $250,000 could go to $300,000, 20% more, "if someone will just commit to actually do the job." His problem isn't work. It's hands.

That cuts two ways for a small shop:

  • You have pricing room. When GCs will pay up just to get a shop to commit, some of that margin can go into the rate, a sign-on bonus or a truck for the hands you need.
  • You need the right hands, not more hands. He wasn't after another apprentice. He needed 1 or 2 working foremen, licensed with 6 to 8 years, who can "lead the job, read the plans, talk to the other trades, then put his tools back on and still run pipe and pull wire." That hire has its own playbook in how to hire a working electrical foreman.

04What it's doing to wages and hiring

Firms on data center jobs report more competition for workers and more wage pressure.

The AGC and NCCER 2026 survey (1,830 respondents, fielded July and August 2026) found 28% of firms worked on a data center project in the past year. Of those:

  • 58% said data centers increased competition for skilled workers.
  • 49% said they saw more wage pressure.
  • 37% said worker or sub availability was their biggest challenge.

Across all firms, more than 8 in 10 raised base pay at least as much as the year before. ABC's Basu said on September 29 that nonresidential contractors "will likely experience faster labor cost escalation" in certain trades "like electricians and HVAC workers."

One national electrical contractor told us they'd tried a travel job board and hiring from neighboring states, and still came up short: "Everybody's just going to these data centers right now." They weren't on a data center job themselves.

05How long will the data center boom keep pulling hands?

Nobody has published an end date. What the data shows is close to a year of data center work already booked, so watch two monthly numbers.

Here's what the data does say:

  • Firms with data center work had 11.3 months of backlog in September 2026 (ABC). That's close to a year of work already under contract.
  • Spending was still climbing in August 2026, up 7.5% in that month alone and growing at a 149% annualized pace since March (ABC).
  • Big waves do end. Chip plant construction spending peaked around 2024 and fell by more than half in two years. When a wave winds down, the hands on it go looking for the next job.

Watch two monthly releases: the Census "Value of Construction Put in Place" numbers and ABC's Construction Backlog Indicator. If data center spending flattens and backlog for those firms drops, the pull eases. Until then, assume it doesn't.

One owner's bet: they come back in two or three years

One open-shop contractor told us data centers and the union hall are both paying big money right now, and he's lost hands to it. His read is that in two or three years, when those jobs are done, the hands will come back looking for steady work. That's his view, not a forecast, and nothing in the Census or ABC numbers puts a date on it.

You don't need to bet on his date to use it. If he's right, the shops that win those hands back are the ones still standing with steady work and a door left open. So:

  • Don't burn the bridge. When a hand leaves for the big rate, shake his hand and tell him the door's open. Write down where he went and when that phase is due to end.
  • Pitch steady work as the long game. "This job runs 14 months and the next one is signed" lands harder on a man who's watched a phase end under him.
  • Judge returners on the work, not the move. A hand who left for a data center and wants to come home isn't a job hopper by default. Our post on hiring a journeyman with a lot of short jobs covers how to tell the difference.

If he's wrong and the work keeps going, you've lost nothing by keeping the door open.

06What a shop without data center work can offer

A journeyman weighs the whole job, not just the rate, and several pieces of that job are yours to win.

What he gets on a big data center jobWhat you can offer instead
A big rate, often with travelA rate close to the market, at home
Long hours while the phase runsSteady hours, with OT when there's OT
A job that ends when the phase endsA next job, and you tell him what it is
One of hundreds on siteA foreman who knows his name and backs him
Badging, long walk-ins, a parking shuttleA truck, a yard and a short drive

Not every data center job looks like the left column, and not every hand wants the right one. But the ones who want the right column are the ones you can keep. The way that commercial contractor put it to us: data center jobs pay, but they aren't forever. Your pitch is the work that's still here when that phase is done.

Home every night

If the nearest data center job is a hotel away, home every night is worth real money to a hand with kids. Put it in the ad in plain words: "Local work. Home every night."

A backlog you can show him

He's afraid of getting short-termed. Tell him how many months of work you have booked and what the next job is. If you can say "this job runs 14 months and the next one is already signed," say it. If you can't, don't fake it.

A rate that holds

Don't make him guess. Post the rate. A rate that stays the same from job to job, with a raise schedule he can see, beats a big number that drops when the phase ends. Our guide to setting a journeyman rate against the market walks through the numbers.

A foreman worth working for

Hands stay for a foreman who knows the work, has material on site and doesn't waste their day. One IEC member contractor wrote that its people stay "even if the hourly pay rate is not as high as other companies" when they see the company investing in their training. That shop runs Saturday classes, quarterly foremen meetings and apprentice tutoring, and says its turnover fell from 114% in 2014 to 15% in 2021.

A crew to run

On a data center job, a good foreman is one of dozens. In a small commercial shop he runs his own crew, deals with the GC and sees a job from layout to trim. For a 6 to 10 year J-man who wants to lead, that's worth more than a few dollars an hour. Say it in the ad: "You'll run your own jobs."

Hours that fit his life

Some hands want 6-10s. Some want 4-10s and a three-day weekend. Ask on the phone screen, and see which schedule keeps electricians before you set yours.

07Where your rate still has to be

You can win without the top rate, but not from the bottom of the market.

BLS puts the national median for electricians at $30.38 an hour, and the top 10% earn more than $108,510 a year, about $52.17 an hour (BLS, May 2025). Those are straight-time wages and include apprentices, so a licensed J-man in a busy market runs above the median. Check your state's numbers, then check live job ads near you.

The same contractor who lost hands to data centers told us they'd been "going higher and higher on the pay rate so we can be competitive." That's normal right now. You don't have to match the data center rate. Get close enough that home every night and a next job tip it your way. If you can't get close, you'll spend the money anyway on OT and turnover.

08Who to go after

Recruit the hands a data center job doesn't fit, and time your calls to when jobs wind down.

  1. Hands with families and roots. Travel and long walk-ins wear on them first.
  2. Hands coming off a big job. When a phase ends or a plant wave winds down, those men want the next job. Be the call they get that week.
  3. Your own former hands. Some left for the big rate. Call them at the six-month mark and ask how it's going.
  4. Foremen who want to run work. Ask who's tired of being one of dozens.
  5. Your crew's buddies. Ask every hand who he'd want on his crew, and pay a referral bonus he can count on.

Then protect who you have. Data center contractors and agencies call your hands too. Our posts on keeping your crew from getting poached and holding a crew until the job is done cover that side.

09A week of moves for a shop short on manpower

  1. Pull your backlog and write down how many months of work you can promise.
  2. Check the BLS median and 90th percentile for your state, then read 10 live ads near you.
  3. Rewrite your ad: rate, hours, home every night, how long the work runs, what's next.
  4. Call every hand who left in the last two years.
  5. Ask your foremen for three names each.
  6. Sit down with your best two hands and ask what would make them leave. Fix what you can.

If you're short now, see the electricians we already have near you. No money up front. If you don't hire, you don't pay.

Got more work than guys?

We already found them: 264 qualified electricians, 5+ years each. See who we have near you. No money up front. If you don't hire, you don't pay.

See who we have

FAQFAQs

Why are so many electricians going to data centers?

Because that's where the money is going. Census data shows private data center construction spending running at $84.95 billion a year in August 2026, up 73% in a year. AGC and NCCER found 49% of firms on data center jobs reported more wage pressure, so those jobs are paying up to staff.

Can a small electrical contractor compete with data centers for electricians?

Yes, for the hands who want what a data center job doesn't give: home every night, steady work and a next job. You won't win every hand. Keep your rate close to the market, post it, and show him your backlog.

Is small commercial work worth chasing while everyone builds data centers?

For a small shop, often yes. Tenant finish-out, restaurants and office work are short on bidders because the big shops are busy elsewhere, and one commercial contractor told us a GC offered to raise a $250,000 bid to $300,000 for any shop that would commit. The catch is having the hands to staff it.

Should I raise my rate to match data center pay?

Usually not all the way. Get close enough to the local market that the rest of your offer tips it. Compare your rate with BLS data for your state and live ads near you, and remember OEWS wages are straight time, not the whole check.

How long will data centers keep pulling electricians?

No one has published a reliable end date. As of September 2026, firms with data center work had 11.3 months of backlog (ABC), close to a year of work under contract. Watch the monthly Census and ABC numbers for the turn.

Do data center jobs make it harder to keep the hands I have?

They can. Big contractors and agencies call working hands with better offers. Keep your crew by telling them what's next, paying on time and paying fairly, and backing your foremen.